Task time estimates for a production line setup project at Robert Klassen’s Ontario factory are as follows

Problem 3.7 Task time estimates for a production line setup project at Robert Klassen’s Ontario factory are as follows:

Activity Time In HRS Immediate Predecessor
A 6 -
B 7.2 -
C 5 A
D 6 B,C
E 4.5 B,C
F 7.7 D
G 4 E,F

a) Develop an AON network for this problem.
b) What is the critical path?
c) What is the total project completion time?