The budget director of Regal Furniture Company requests estimates of sales, production, and other operating data from the various administrative units every month

The budget director of Regal Furniture Company requests estimates of sales, production, and other operating data from the various administrative units every month. Selected information concerning sales and production for August 2010 is summarized as follows:
a. Estimated sales of King and Prince chairs for August by sales territory:
Northern Domestic:
King.........................5,500 units at $750 per unit
Prince......................6,900 units at $520 per unit

Southern Domestic:
King.........................3,200 units at $690 per unit
Prince......................4,000 units at $580 per unit

International:
King........................1,450 units at $780 per unit
Prince......................900 units at $600 per unit

b. Estimated inventories at August 1:
Direct materials:
Finished Products
Fabric................4,500 sq. yds
King.....................950units
Wood.................6,000 lineal ft.
Prince..................280units
Filler...................2,800 cu, ft
Springs..............6,700 units

c. Desired inventories at August 31:
Direct Materials:
Finished Products:
Fabric..................4300 sq yds
King.............800units
Wood..................6,200 lineal ft.
Prince...........400units
Filler....................3,100 cu. ft
Springs................7,500 units

d. Direct materials used in production:
In manufacture of King:
Fabric..................5.0 sq. yds per unit of product
Wood ..................35 lineal ft. per unit of product
 Filler.................... 3.8 cu ft. per units of product
Springs.................14 units per units of product

In manufacture of Prince:
Fabric...............$12.00 per sq. yd.
Filler..............$3.50 per cu. ft.
Wood................ 8.00 per lineal ft.
Springs........... 4.50 per unit

f. Direct labor requirements:
King:
Framing Department............ 2.5hrs. at $12 per hr.
Cutting Department.............. 1.5 hrs. at $11 per hr.
Upholstery Department.......... 2.4hrs. at $14 per hr.
Prince: Framing Department............ 1.8 hrs. at $12 per hr.
Cutting Department............. 0.5 hrs. at $11 per hr.
Upholstery Department......... 2.0hrs. at $14 per hr.

3.) Prepare a direct materials purchases budget for August.
4.)Prepare a direct labor cost budget for August

Click here for the solution: The budget director of Regal Furniture Company requests estimates of sales, production, and other operating data from the various administrative units every month

Friday, October 9, 2015

The budget director of Outdoor Gourmet Grill Company requests estimates of sales, production, and other operating data

The budget director of Outdoor Gourmet Grill Company requests estimates of sales, production, and other operating data from the various administrative units every month. Selected information concerning sales and production for July 2010 is summarized as follows:

a. Estimated sales for July by sales territory:
Maine:
Backyard Chef...........................5000 units at $750 per unit
Master Chef..............................1800 units at $1,500 per unit
Vermont:
Backyard Chef..........................4200 units at $800 per unit
Master Chef.............................1600 units at $1,600 per unit
New Hampshire:
Backyard Chef..........................4600 units at $850 per unit
Master Chef.............................1900 units at $1,700 per unit

b. Estimated inventories at July 1:
Direct materials: Finished products:
Grates.....................1000 units Backyard chef........1400 units
Stainless steel...........1800 lbs Master Chef........... 600 units
Burner subassemblies....500 units
Shelves.................... 300 units

c. Desired inventories at July 31:
Direct materials: Finished products:
Grates..................... 800 units Backyard chef........1600 units
Stainless steel........... 2100 lbs Master Chef........... 500 units
Burner subassemblies....550 units
Shelves.................... 350 units

d. Direct materials used in production:
In manufacture of Backyard Chef:
Grates.......................... 3 units per unit of product
Stainless steel................ 20 lbs per unit of product
Burner subassemblies....... 2 units per unit of product
Shelves......................... 5 units per unit of product
In manufacture of Master Chef:
Grates.......................... 6 units per unit of product
Stainless steel................ 45 lbs per unit of product
Burner subassemblies....... 4 units per unit of product
Shelves......................... 6 units per unit of product

e. Anticipated purchase price for direct materials:
Grates.............. $20 per unit Burner subassemblies...... $105 per unit
Stainless steel...... $6 per lb Shelves.........................$7 per unit

f. Direct labor requirements:
Backyard Chef:
Stamping Dept. 0.60 hr at $18 per hr
Forming Dept. 0.80 hr at $14 per hr
Assembly Dept. 1.50 hr at $12 per hr
Master Chef:
Stamping Dept. 0.80 hr at $18 per hr
Forming Dept. 1.50 hr at $14 per hr
Assembly Dept. 2.50 hr at $12 per hr

1. Prepare a sales budget for July.
2. Prepare a production budget for July.
3. Prepare a direct materials purchases budget for July.
4. Prepare a direct labor cost budget for July.

Click here for the solution: The budget director of Outdoor Gourmet Grill Company requests estimates of sales, production, and other operating data

Sunday, September 20, 2015

Task time estimates for a production line setup project at Robert Klassen’s Ontario factory are as follows

Problem 3.7 Task time estimates for a production line setup project at Robert Klassen’s Ontario factory are as follows:

Activity Time In HRS Immediate Predecessor
A 6 -
B 7.2 -
C 5 A
D 6 B,C
E 4.5 B,C
F 7.7 D
G 4 E,F

a) Develop an AON network for this problem.
b) What is the critical path?
c) What is the total project completion time?


Click here for the solution: Task time estimates for a production line setup project at Robert Klassen’s Ontario factory are as follows

Friday, August 14, 2015

Assume that a country estimates its M1 money supply at $20 million

8. Assume that a country estimates its M1 money supply at $20 million. A broader measure of the money supply, M2, is $50 million. The country’s gross domestic product is $100 million. Production or real output for the country is 500,000 units or products.

a. Determine the velocity of money based on the M1 money supply.
b. Determine the velocity of money based on the M2 money supply.
c. Determine the average price for the real output.

Click here for the solution: Assume that a country estimates its M1 money supply at $20 million

Tuesday, July 14, 2015

Final earnings estimates for Chilean Health Spa & Fitness Center have been prepared for the CFO of the company and are shown in the following table

(Dividend policies) Final earnings estimates for Chilean Health Spa & Fitness Center have been prepared for the CFO of the company and are shown in the following table. The firm has 7,500,000 shares of common stock outstanding. As assistant to the CFO, you are asked to determine the yearly dividend per share to be paid depending on the following possible policies:

YEAR PROFITS AFTER TAXES
1 $ 18,000,000
2 21,000,000
3 19,000,000
4 23,000,000
5 25,000,000

a. A stable dollar dividend targeted at 40 percent of earnings over a 5-year period
b. A small, regular dividend of $0.60 per share plus a year-end extra when the profits in any year exceed $20,000,000. The year-end extra dividend will equal 50 percent of profits exceeding $20,000,000.
c. A constant dividend payout ratio of 40 percent

Click here for the solution: Final earnings estimates for Chilean Health Spa & Fitness Center have been prepared for the CFO of the company and are shown in the following table

Monday, July 6, 2015

The budget director of Outdoor Chef Grill Company requests estimates of sales, production, and other operating data from the various administrative units every month

The budget director of Outdoor Chef Grill Company requests estimates of sales, production, and other operating data from the various administrative units every month. Selected information concerning sales and production for May 2012 is summarized as follows:

a. Estimated sales for May by sales territory:
b. Estimated inventories at May 1:
c. Desired inventories at May 31:
d. Direct materials used in production:
e. Anticipated purchase price for direct materials:
f. Direct labor requirements:

Required;
1. Prepare a sales budget for May.
2. Prepare a production budget for May.
3. Prepare a direct materials purchases budget for May.
4. Prepare a direct labor cost budget for May

Check: 3. Total Direct Materials Purchases, $939,065

Click here for the solution: The budget director of Outdoor Chef Grill Company requests estimates of sales, production, and other operating data from the various administrative units every month