Problem 3.3 Draw the activity-on-node (AON) project network associated
with the following activities for Dave Carhart’s consulting company
project. How long should it take Dave and his team to complete this
project? What are the critical path activities?
Activity Immediate Predecessor Days
A - 3
B A 4
C A 6
D B 6
E B 4
F C 4
G D 6
H E,F 8