Sunday, September 20, 2015

The following is a table of activities associated with a project at Bill Figg Enterprises, their durations and what activities each must precede

Problem 3.15 The following is a table of activities associated with a project at Bill Figg Enterprises, their durations and what activities each must precede:

ACTIVITY DURATION (WEEKS) PRECEDES
A (START) 1 B,C
B 1 E
C 4 F
E 2 F
F(END) 2 -

a) Draw an AON diagram of the project, including activity durations.
c) What is the project duration (in weeks)?
d) What is the slack (in weeks) associated with any and all noncritical paths through the project?


Click here for the solution: The following is a table of activities associated with a project at Bill Figg Enterprises, their durations and what activities each must precede

Bill Fennema, president of Fennema Construction, has developed the tasks, durations, and predecessor relationships

Problem 3.17 Bill Fennema, president of Fennema Construction, has developed the tasks, durations, and predecessor relationships in the following table for building new motels. Draw the AON network and answer the questions that follow.

Activity Immediate Predecessor Optimistic Most Likely Pessimistic
A - 4 8 10
B A 2 8 24
C A 8 12 16
D A 4 6 10
E B 1 2 3
F E,C 6 8 20
G E,C 2 3 4
H F 2 2 2
I F 6 6 6
J D,G,H 4 6 12
K I,J 2 2 3

a) What is the expected (estimated) time for activity C?
c) Based on the calculation of estimated times, what is the critical path?
d) What is the estimated time of the critical path?


Click here for the solution: Bill Fennema, president of Fennema Construction, has developed the tasks, durations, and predecessor relationships