Sunday, September 20, 2015

Refer to Problem 4.2. Develop a forecast for years 2 through 12 using exponential smoothing with a= .4 and a forecast for year 1 of 6

Problem 4.3 Refer to Problem 4.2. Develop a forecast for years 2 through 12 using exponential smoothing with a= .4 and a forecast for year 1 of 6. Plot your new forecast on a graph with the actual data and the naive forecast. Based on a visual inspection, which forecast is better
Year 1 2 3 4 5 6 7 8 9 10 11
Demand 7 9 5 9 13 8 12 13 9 11 7


Click here for the solution: Refer to Problem 4.2. Develop a forecast for years 2 through 12 using exponential smoothing with a= .4 and a forecast for year 1 of 6

Thursday, July 2, 2015

Tylon's Hardware uses a flexible budget to develop planning information for its warehouse operations

Tylon's Hardware uses a flexible budget to develop planning information for its warehouse operations. For 20X2, the company anticipated that it would have 96,000 sales units for 664 customer shipments. Average storage bin usage for various inventories was estimated to be 200 per day. The costs and cost drivers were determined to be as follows:

Item Fixed Variable Cost driver
Product handling $10,000 $1.25 per 100 units
Storage - 3.00 per storage bin
Utilities 1,000 1.50 per 100 units
Shipping clerks 1,000 1.00 per shipment
Supplies - 0.50 per shipment

During the year, the warehouse processed 90,000 units for 600 customer shipments. The workers used 225 storage bins on average each day to sort, store, and process goods for shipment. The actual costs for 20X2 were:

Item Actual costs
Product handling $10,900
Storage 465
Utilities 2,020
Shipping clerks 1,400
Supplies 340

Question 1: Determine the 20X2 static budget variances.
Question 2: Determine the 20X2 flexible budget variances.

Click here for the solution: Tylon's Hardware uses a flexible budget to develop planning information for its warehouse operations