Fixed Variable Cost driver
Product handling $30,000 $0.40 per unit
Inspection 8,000 8.00 per 100 unit batch
Utilities 400 4.00 per 100 unit batch
Maintenance 1,000 0.20 per machine-hour
Supplies 5.00 per employee day
During the year, the company processed 20,000 units, worked 7,500 employee days, and had 4,000 machine-hours. The actual costs for 20x4 were:
Actual costs
Product handling $36,000
Inspection 9,000
Utilities 1,600
Maintenance 1,200
Supplies 37,500
Required:
a. Prepare the static budget using the overhead items above and then compute the static-budget variances.
b. Prepare the flexible budget using the overhead items above and then compute the flexible-budget variances.