On February 1, 2007, Reardon Corporation purchased a parcel of land as a factory site for $320,000. An old building on the property was demolished and construction begun on a new warehouse that was completed April 15, 2008. Costs incurred on the construction project are listed below.
Demolition of old building $21,000
Architect's fees 31,700
Legal fees/title investigation 4,100
Construction costs 950,000
Imputed interest based on stock financing 14,000
Landfill for building site 19,300
Clearing of trees from the building site 9,600
Temporary buildings used for construction activities 29,000
Land survey 4,000
Excavation for basement 13,200
(Salvage materials from demolition sold for $1,800)
(Timber sold for $3,300)
Determine the cost of the land and new building.
Click here for the solution: On February 1, 2007, Reardon Corporation purchased a parcel of land as a factory site for $320,000