Search This Blog

Sunday, July 19, 2015

Smith Construction Company was awarded a contract to construct an interchange at the junction of Interstate 5 and US Highway 27 at a total contract price of $8,000,000

Smith Construction Company was awarded a contract to construct an interchange at the junction of Interstate 5 and US Highway 27 at a total contract price of $8,000,000. The estimated total costs to complete the project were $6,000,000.

Instructions
(a) Make the entry to record construction costs of $3,600,000, on construction in process to date.
(b) Make the entry to record progress billings of $2,000,000.
(c) Make the entry to recognize the profit that can be recognized to date, on a percentage-of-completion basis.

Click here for the solution: Smith Construction Company was awarded a contract to construct an interchange at the junction of Interstate 5 and US Highway 27 at a total contract price of $8,000,000