Edwards Company contracted on 4/1/10 to construct a building for
$2,500,000. The project was completed in 2012. Additional data follow:
2010 2011 2012
Costs incurred to date $ 560,000 $1,350,000 $1,900,000
Estimated cost to complete 1,040,000 450,000 —
Billings to date 500,000 2,000,000 2,500,000
Collections to date 400,000 1,300,000 2,400,000
Instructions
(a) Calculate the income recognized by Edwards under the
percentage-of-completion method of accounting in each of the years 2010,
2011, and 2012.
(b) Prepare all necessary entries for the year 2011.
Click here for the solution: Edwards Company contracted on 4/1/10 to construct a building for $2,500,000
Search This Blog
Showing posts with label contracted. Show all posts
Showing posts with label contracted. Show all posts
Tuesday, September 8, 2015
Saturday, August 1, 2015
On July 1, 2010, Torvill Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,900,000
P18-7 (Long-Term Contract with an Overall Loss) On July 1, 2010, Torvill Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,900,000. On July 1, Torvill estimated that it would take between 2 and 3 years to complete the building. On December 31, 2012, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2010, 2011, and 2012.
At At At
12/31/10 12/31/11 12/31/12
Contract costs incurred to date $ 300,000 $1,200,000 $2,100,000
Estimated costs to complete the contract 1,200,000 800,000 –0–
Billings to Gumbel 300,000 1,100,000 1,850,000
Instructions
(a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2010, 2011, and 2012. (Ignore income taxes.)
(b) Using the completed-contract method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2010, 2011, and 2012. (Ignore income taxes.)
Click here for the solution: On July 1, 2010, Torvill Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,900,000
At At At
12/31/10 12/31/11 12/31/12
Contract costs incurred to date $ 300,000 $1,200,000 $2,100,000
Estimated costs to complete the contract 1,200,000 800,000 –0–
Billings to Gumbel 300,000 1,100,000 1,850,000
Instructions
(a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2010, 2011, and 2012. (Ignore income taxes.)
(b) Using the completed-contract method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2010, 2011, and 2012. (Ignore income taxes.)
Click here for the solution: On July 1, 2010, Torvill Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,900,000
Tuesday, June 23, 2015
On July 1, 2007, Kyung-wook Construction Company Inc. contracted to build an office building for Mingxia Corp. for a total contract price of $1,950,000
Problem 18-7 (P18-7) (Long-Term Contract with an Overall Loss) On
July 1, 2007, Kyung-wook Construction Company Inc. contracted to build
an office building for Mingxia Corp. for a total contract price of
$1,950,000. On July 1, Kyung-wook estimated that it would take between 2
and 3 years to complete the building. On December 31, 2009, the
building was deemed substantially completed. Following are accumulated
contract costs incurred, estimated costs to complete the contract, and
accumulated billings to Mingxia for 2007, 2008, and 2009.
At At At
12/31/07 12/31/08 12/31/09
Contract costs incurred to date $ 150,000 $1,200,000 $2,100,000
Estimated costs to complete the contract 1,350,000 800,000 –0–
Billings to Mingxia 300,000 1,100,000 1,850,000
Instructions
(a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2007, 2008, and 2009. (Ignore income taxes.)
(b) Using the completed-contract method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 2007, 2008, and 2009. (Ignore income taxes.)
Click here for the solution: On July 1, 2007, Kyung-wook Construction Company Inc. contracted to build an office building for Mingxia Corp. for a total contract price of $1,950,000
At At At
12/31/07 12/31/08 12/31/09
Contract costs incurred to date $ 150,000 $1,200,000 $2,100,000
Estimated costs to complete the contract 1,350,000 800,000 –0–
Billings to Mingxia 300,000 1,100,000 1,850,000
Instructions
(a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2007, 2008, and 2009. (Ignore income taxes.)
(b) Using the completed-contract method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 2007, 2008, and 2009. (Ignore income taxes.)
Click here for the solution: On July 1, 2007, Kyung-wook Construction Company Inc. contracted to build an office building for Mingxia Corp. for a total contract price of $1,950,000